THE PROJECT IS ON SCHEDULE AND PROCEEDING VERY WELL.
THE 3rd FLOOR IS NEARING COMPLETION, WITH SUITES PAINTED,
CEILINGS STIPLED, CABINETS INSTALLED, ELECTRICAL OUTLETS
INSTALLED. FLOORING WILL START ON MONDAY, MARCH 14th
THE SECOND FLOOR IS CURRENTLY BEING PAINTED AND THE MAIN
FLOOR IS BEING DRYWALLED.
THE ELEVATOR IS 85% COMPLETE.
HEATING UNITS WILL START TO BE INSTALLED NEXT WEEK AS WILL
PLUMBING FIXTURES. DOORS AND MOLDINGS ARE BEING INSTALLED.