Wednesday, December 22, 2010

UPDATE - DECEMBER 22nd, 2010

ELECTRICAL CONTRACTOR VERN
AND
SITE SUPERVISOR LESTER
CHECK OUT THE BIG PANELS FOR THE
NEW BUILDING


HALL WAY ON MAIN FLOOR


ALL OF THE 2 BR SUITES FACING
EAST, ON 3RD FLOOR HAVE BEEN
BOARDED


2 BR SUITE LOOKING BACK TO THE
DOOR LEADING TO THE HALL AND
THE COAT CLOSET AT THE ENTRANCE


2nd BR OF ONE OF THE
2 BR SUITES


CLOSET IN MAIN BR
OF 2 BR SUITE


MEDICINE CABINET HOLE
IN BATHROOM


HALL WAY ON 3rd FLOOR


VIEW FROM BALCONY ON
3rd FLOOR


FRONT ROOM OF ONE BR SUITE


MAIN ELECTRICAL PANELS FOR
THE BUILDING


ONE OF THE TEMPORARY HEATERS


TEMPORARY ELECTRICAL PANEL

Wednesday, December 8, 2010

UPDATE - DECEMBER 7th, 2010

ON TUESDAY, DECEMBER 7th  ANOTHER
SITE MEETING WAS HELD.

THE PROJECT IS RUNNING CLOSE TO
SCHEDULE






SITE SUPERVISOR
LESTER THIESSEN


MIKE McGINN AND ROBERT SOBIAK
INSPECT THE WORK


BRETT CAMERON of TL PENNER CONST.


VIEW IN A 2 BR SUITE



Friday, November 26, 2010

UPDATE - NOVEMBER 25TH

THE BOLTON BAY SENIOR SUITES ARE PROGRESSING VERY WELL AND ON SCHEDULE FOR COMPLETION IN JUNE 2011.   CURRENTLY TENANTS ARE REVIEWING OPTION PACKAGES TO COMPLETE THEIR SUITES.   THESE PACKAGES INCLUDE:

  - CHOICES  OF:
             - FLOORING
             - PAINT COLORS
             - COUNTER AND VANITY TOPS
             - FLOOR COVERING IN BATHROOM AND UTILITY ROOM
             - ISLAND
             - SHELVING FOR UTILITY ROOM

  - REVIEW OF:
             - SOLID OAK CUPBOARDS
             - APPLIANCES ( REFRIGERATOR, STOVE, DISHWASHER, WASHER AND DRYER

THERE ARE STILL 14 SUITES LEFT TO LEASE.  IF YOU ARE INTERESTED, PLEASE CONTACT JIM LYONS OR DOUG McLELLAN

COMMON ROOM


VIEW FROM BALCONY


KITCHEN IN SUITE ON 3RD


SUITE ON3RD FLOOR


HALLWAY ON 3RD FLOOR


ELEVATOR SHAFT ON 3RD


Wednesday, November 3, 2010

UPDATE - NOVEMBER 1st

THE REGULAR MONTHLY SITE
MEETING WAS HELD ON
MONDAY, NOV 1st, 2010

REPRESENTATIVES OF
McGINN ARCH AND ENGINEERING
TL PENNER CONSTRUCTION
MANITOBA HOUSING
VIRDEN CENTENNIAL HOUSING CORP

MET TO REVIEW THE PROJECT
EVERYTHING SEEMS TO BE RUNNING SMOOTHLY
AND ON SCHEDULE
--------------------------------------------

BALCONY ON THE MAIN FLOOR




FRONT ENTRANCE


KITCHEN FROM THE COMMON ROOM


FRONT ENTRANCE FROM THE COMMON
ROOM


SITE INSPECTION


SITE SUPERVISOR - LESTER TOEWS

AND MANITOBA HOUSING REPS
- ROBERT SOBIAK
- JACQUES GAUTHIER


UPDATE - OCTOBER 28th

VIRDEN CENTENNIAL HOUSING CORP
DIRECTORS
CAROL WILSON AND PAT LYONS
CO-PROJECT MGRs
JIM LYONS AND DOUG McLELLAN
visit the project on Oct 28th to
help in making a decorating
decision
SITE SUPERVISOR LESTER TOEWS
ASSISTED IN IDENTIFYING THE
QUESTION



DRYWALL BEING HOISTED INTO
THE 3RD FLOOR





CAROL, PAT AND LESTER
SIZING UP THE SITUATION

Wednesday, October 20, 2010

UPDATE - OCTOBER 20th


WORKING ON BOLTON BAY
CRESCENT


OCTOBER 19th





PUTTING ON THE SIDING




Thursday, October 7, 2010

UPDATE - OCT 6th, 2010


INSTALLING WINDOWS
AND DOORS














Tuesday, September 28, 2010

UPDATE - SEPT 28th

FALL IN VIRDEN
LOOKING DOWN THOMAS DRIVE


Sept 26th
Shingling almost complete


SEPT 27th


OUTDOOR PATIO
&
MECHANICAL ROOM


OUTDOOR PATIO AREA


WORKING ON BALCONY


SEPT 28th
ROOF COMPLETE


WEST SIDE OF BUILDING


WEST SIDE OF BUILDING
SEPT 28th